How to track change orders on a small remodel

Keep the original approved quote, approved changes and pending requests separate.

Freeze an approved baseline

Save the accepted scope, selling price and estimated job cost with a revision date. For example, an $8,000 accepted quote with $6,000 estimated cost is your original baseline. Do not overwrite those numbers when the client asks for extra work.

Record each request separately

Give each request an ID, date, scope, estimated cost, proposed price and status. Keep evidence of approval, and document any time impact. A request for $500 additional work with $350 additional cost should remain pending until approval is documented. Follow the contract and local requirements for approval.

Update the forecast only when appropriate

After approval, revised selling price is $8,500 and revised cost budget is $6,350. Budgeted profit is $2,150 before tax. If another request is pending, track it separately as a risk or scenario, not approved revenue. A credit or omitted item should reduce the appropriate amounts rather than be treated as extra income.

Reconcile at the end of the job

Compare the approved selling price to actual costs and reconcile unpaid invoices separately. Keep a record of changes and supporting receipts. A change order log is not a substitute for signed contractual documentation or professional advice.

Related guides